Post-Installed Anchors: Approve the Application, Then Release the Work
A passing pull test is only one piece of the evidence. Connect anchor selection, actual site conditions, witnessed installation and permission to load on Iranian projects.

Approve the application before accepting the delivery
Treat a post-installed anchor as a designed connection with an installation history, not as a box of threaded rods. OlbrichCo’s recommendation is to make three decisions separately: whether the selected system suits the application, whether the site can install it as specified, and whether the installed connection can be released for loading. One signature should not silently answer all three.
ACI CODE-355.4-24 addresses adhesive-anchor qualification for conditions including sustained and seismic loading, temperature and cracked concrete. ACI CODE-355.2-24 addresses mechanical-anchor qualification for static and seismic actions. These are qualification frameworks, not interchangeable product approvals. [1][2]
For an Iranian project, ask the responsible structural engineer to issue an anchor schedule tied to actual supports: equipment bases, façade brackets, steel connections or service hangers. Record the load cases, host concrete, geometry, exposure and governing design basis. Keep reinforcing-bar development connections outside this workflow unless separately designed; a similar-looking drilled hole does not establish the same application.
Before inviting substitutions, agree who evaluates them and how programme consequences are priced in the contract. Request the exact product designation, current assessment, permitted installation conditions and manufacturer’s instructions together. Do not accept a brochure strength value as the design of an anchor group. Where evidence cannot be obtained for the delivered product and application, hold procurement or obtain an engineered alternative.
Make the site conditions part of product selection
Use a short application sheet beside each schedule entry. Ask the designer to resolve concrete strength and condition, cracked-concrete assumptions, edge distances, spacing, member thickness, effective embedment and fixture geometry. Record sustained, seismic or other relevant actions explicitly. Mark unknowns as unresolved; do not let an empty field acquire an optimistic default when it reaches the installer.
For renovation, commission a scoped survey of the host member and the intended drilling zone. Agree how reinforcement, prestressing and embedded services will be identified, what uncertainty remains and who authorises drilling. If a hole meets an obstruction, stop that location. Moving the hole, cutting reinforcement or shortening embedment needs a design decision, not a sketch added after installation.
Make climate a measured input rather than a city-wide assumption. Request the selected system’s permitted storage, installation and service conditions. Plan how the crew will record the temperatures and hole conditions required by those instructions. A shaded interior slab, sun-exposed roof and damp basement should not share an unexamined method statement simply because the same cartridge arrives on site.
Review the local support chain before purchase: can the specified drill system, cleaning accessories, dispenser, mixing components, steel elements and inspection equipment actually be supplied and maintained? Ask for a practical demonstration using the proposed kit. This is a project procurement check, not a claim about nationwide availability or an endorsement of any brand. Escalate an unavailable component before approving the package.
Witness the process while the evidence is visible
Hilti’s technical explanation identifies the hole-wall condition as important to adhesive bonding and notes that adhesive anchors require curing, with time affected by temperature. Use the selected product’s instructions for the actual drilling, cleaning, injection and curing sequence. [3]
Arrange a first-installation demonstration with the intended crew, supervisor and inspector before repetitive work. Check document revisions, product identity and expiry, storage records, hole geometry, approved drilling method, cleaning equipment and the required installation sequence. Confirm that instructions are understood in Persian or the crew’s working language. A translated work card should reference the controlled original, not replace it.
Put witness points before information disappears: drilling and hole acceptance before insertion, installation records before concealment, and completion of the specified curing or setting process before loading. Ask the installer to show how completion is identified at the work front. A photograph of a finished rod cannot, by itself, document the earlier condition of the hole or the full sequence.
For adhesive systems, plan a protected curing interval and an explicit release time derived from the selected instructions and recorded conditions. Keep other trades from disturbing or loading the connection during that interval. For mechanical systems, verify the specified setting and tightening procedure instead. Never borrow a torque, cleaning count, cure time or reuse rule from a neighbouring product.
Specify what a site test can—and cannot—answer
AEFAC distinguishes installation proof tests from tests intended to establish strength. Its guidance warns that short-term proof testing cannot investigate creep or establish product suitability for the substrate; adhesive anchors must complete the specified curing period before proof testing. [4]
AEFAC also treats changes in fastener, substrate, installation method or personnel as boundaries between test populations. Its proof-test guidance places load selection with the responsible engineer and requires investigation when a test fails. [5]
If testing is required, have the engineer issue the purpose, population, sampling plan, test load, duration, acceptance criteria, reaction arrangement and failure response before a tester is booked. Include calibration, safe exclusion, access and reporting requirements. Ask whether displacement matters to the supported assembly. Do not give the tester only a percentage of anchors and ask them to invent the rest.
Choose between additional investigation, a different qualified system and an engineered redesign when the application sits outside the evidence. More pull tests are not an automatic solution. Avoid a contract that pays solely for passing certificates: require a mapped record of every attempted test, including failures and interrupted tests, and a signed engineering disposition before affected work is released.
Release a defined population and control its changes
Keep one record linking the support location to the approved detail, product and batch, installer, date, method revision, observations, curing or setting evidence, inspection and any test report. Define the population boundaries before work starts. A floor-wide approval should not conceal a change of crew, product, drilling method or host condition halfway through the shift.
Use simple offline records where site connectivity is uncertain: numbered paper sheets or a local form, a marked-up location drawing and photographs with matching identifiers. Assign one person to reconcile them into the owner-held register. Record uncertainty honestly. A missing pre-insertion observation should trigger review of the affected population, not retrospective completion of a checklist from memory.
Agree the hold points in the inspection plan and programme. Suggested release states are: application approved; drilling authorised; installation accepted; loading authorised. Name who may advance each state and who can withdraw it. Keep a visible hold on an unresolved connection, and coordinate temporary support with the responsible engineer rather than allowing the next trade to discover the hold after lifting.
When a test fails or installation departs from instructions, identify and hold the relevant population, preserve the evidence and obtain an engineering response. Do not repeatedly test replacement anchors until one passes while leaving the cause unknown. Record the authorised repair, any revised sampling and the final disposition. Apply the same change review when later equipment replacement changes the connection demand.
Measure a repeatable release, not a count of green marks
Pilot the workflow on one repeatable support family with meaningful consequences. Before rollout, walk the designer, buyer, installer and inspector through a real location: identify the approved product, find the instructions, show the drilling permission, trace the batch and locate the loading release. Resolve gaps before using the process on the remaining locations.
Track the share of locations with complete application records before drilling, installations witnessed at the agreed stages, loads released with complete evidence, unapproved substitutions, missing records, test failures and time to close engineering dispositions. Report by product, crew and host condition. Set project targets before the pilot; do not turn the first convenient result into the acceptance threshold.
Compare the actual effort for documentation, access, consumables, protection, inspection, tests and rework against the tender assumptions. Treat this as a project learning exercise, not a promised return on investment. If records are too burdensome to maintain, simplify duplicate entry while retaining the connection identity, critical observations and accountable release decision.
The deliverable is a connection whose design basis, installation and release can be reconstructed by the next responsible person. Applicable Iranian requirements, the contract, selected product documents, site conditions and competent local engineering review control the final decisions. This note provides no universal anchor dimensions, test loads, sampling percentages or permission to load; those must be specified for the actual work.
Sources & further reading
These primary sources support the claims and implementation frameworks used in this field note.
- 1. ACI CODE-355.4-24 — Post-Installed Adhesive Anchors in Concrete: Qualification Requirements and Commentary (public abstract)
American Concrete Institute
- 2. ACI CODE-355.2-24 — Post-Installed Mechanical Anchors in Concrete: Qualification Requirements and Commentary (public scope)
American Concrete Institute
- 3. What is the Difference Between Mechanical vs. Adhesive Post-Installed Anchors?
Hilti
- 4. AEFAC TN05 — Site Testing Guidelines, Volume 1: General
Australian Engineered Fasteners and Anchors Council
- 5. AEFAC TN05 — Site Testing Guidelines, Volume 2: Proof Tests
Australian Engineered Fasteners and Anchors Council
Sources checked on 29 September 2026. ACI references are public scope summaries, not a review of the full licensed codes. Cited paragraphs summarise source material; uncited workflow proposals are OlbrichCo analysis. Foreign guidance is not presented as Iranian law. The cover is conceptual, not a product or installation detail.